How Much Concrete Do I Need for a Sidewalk? Joints Should Match the Width
A sidewalk is length × width × thickness, then ÷ 27 for cubic yards.
A worked example: a 50 ft × 4 ft sidewalk at 4 in thick
- Volume: 50 × 4 × (4 ÷ 12) = 66.67 cubic feet
- Cubic yards: 66.67 ÷ 27 = 2.47 cubic yards
- With 10% waste: 2.72 cubic yards — 123 × 80 lb bags
Thickness and mix
Sidewalks are typically poured 4 in thick (minimum 3 in) with a 3,000 PSI mix; step up to 5–6 in where vehicles cross.
Control joints
Match the control joints to the walk width for square panels — a 4 ft walk gets joints every 4 ft, so the 50 ft walk needs 13 control joints — and cut them at least a quarter of the slab thickness deep, or the cracks will wander. Hold a 1–2% cross slope so water runs off (2% is the maximum for comfortable walking), and keep an expansion joint where the walk meets the foundation, steps or driveway.
A smaller walkway
A smaller 30 ft × 3 ft walkway at 4 in is 30 cubic feet = 1.11 cubic yards, 55 bags with waste, 10 joints and 99 sq ft of wire mesh with overlap.
If you would rather not do the arithmetic by hand, run the same numbers through a sidewalk concrete calculator — it gives volume, bags, joints and mesh in one step.